It’s amazing what can happen in just a few days.  The last series of photos included erecting the walls.  Now we have a roof (with roof shingles), windows, all framing, plumbing rough in, HVAC rough in, and tomorrow we’ll have an exterior door installed and electrical rough in.  Oh yea, removal of the existing wall to the family room and re-framing for the new French doors.  Then come the four major Wake County inspections: plumbing, HVAC, electrical and framing.  All should be good to go at that point for insulation and drywall.