Holly Springs 2nd floor project shaping up

Hi everyone, Pleased as punch to share information about the Holly Springs attic project. The plumbing rough in inspection passed today, the HVAC unit was placed in the attic along with all of the ductwork (photos soon), most of the framing will finish tomorrow, and the electrician is scheduled for early next week for his rough wiring. Attached photos show the before and after of the front gable going from one window to three. What a difference it makes on the inside with all of the natural light streaming in.